Highview Stage 3 Jindabyne (client Northrop Consulting Engineers)

Ecowise Services was awarded the electrical (powerline) reticulation of this estate. This was a relatively standard Level 1 construction project, with the following fundamentals:


  • 300m of 11kV 240sqmm underground cable;
  • 1200m of LV 240sqmm underground cable;
  • 22 LV pillars;
  • 2 padmount substations plus 1 HV gas switch;
  • 10 streetlight columns;
  • Several stages of temporary HV overhead augmentation to keep the feeder supplying neighbouring loads over several months.


Ecowise Services routinely travels to regional areas for powerline and other construction works.

Our other projects.

02 Nov, 2023
Ecowise Services was engaged to undertake early assembly and refinement of the major prototype building blocks, including most of the elements of internal fitout (ie trunk data circuits, all power elements, container interconnection and UPS/Rack final mounting).